Unsigned T&M tickets and T&M disputes: how to get paid for the work
Time-and-material work is only as good as the ticket behind it. When the GC's super won't sign, signs a week later, or signs and then disputes the hours, the electrical contractor carries the cost. Here is how to keep tickets signed, what to do when they aren't, and how to argue a disputed ticket.
Why T&M tickets go unsigned
- The super wasn't on the floor when the work was done and won't sign for what he didn't see.
- The foreman fills it out at the end of the week from memory, and the hours look padded.
- The work is in dispute: the GC thinks it's base scope, so signing feels like admitting it's extra.
- The super signs "for time only," or isn't authorized to sign at all under the subcontract.
- The ticket sits in a truck and never reaches the office.
Get it signed the same day
The single best fix is timing. A ticket presented the day of the work, while the crew is still standing there, gets signed far more often than one presented on Friday for Tuesday's work.
- Tie every ticket to its directive: the CCD, RFI, email or verbal direction, with the name of the person who gave it and when.
- List each worker by name and classification with regular and overtime hours, plus material and equipment with quantities.
- Describe the work in a sentence the super can verify by walking over and looking.
- Take photos before, during and after. They settle most arguments about what was done.
- Get the signature with the signer's printed name, title and company. Check your subcontract for who is authorized to sign.
When the super won't sign
Don't stop documenting just because the signature line is blank.
- Send the unsigned ticket the same day by email to the super and the GC's PM, with photos, asking them to sign or tell you in writing what they dispute. An email that goes unanswered is still a record.
- Note the refusal on the ticket: date, time, and who declined to sign.
- If the work itself is disputed, send written notice of change within your subcontract's notice period. The ticket is the cost record; the notice protects the claim.
- Keep daily reports and timesheets that match the ticket hours. Matching records are hard to dismiss even without a signature.
- If a super refuses as a pattern, raise it with the GC's PM in writing and ask who on their side is authorized to sign.
Arguing a disputed ticket
When the GC cuts the hours
Ask for the reduction in writing with the reason. Answer with the crew list, daily reports, photos and the sequence of the work. If part of the dispute is fair (a lunch hour, a duplicate entry), concede that piece quickly so the rest of the ticket gets paid.
When the GC says it's base scope
That's an entitlement argument, not a ticket argument. Point to the drawings, specs, RFI answers or directives that show the work is outside your contract, and keep tracking cost on the ticket while it is decided.
When tickets add up past a not-to-exceed
Track cost to date against the NTE every week, including tickets that aren't signed yet, and ask for an increase in writing before you reach it. More on CCDs and NTEs.
Common mistakes
- Writing tickets at the end of the week instead of the end of the day.
- No directive reference, so nobody can tell what the work was for.
- One line of "misc. electrical work, 16 hrs" with no detail.
- Letting unsigned tickets pile up without a same-day email.
- Treating a signed ticket as an approved change order and never pricing it formally.
Need a ticket format? Free T&M ticket template.
Where software helps
In Electrical Change Orders the foreman builds the T&M ticket on a phone with crew, hours, material and photos, and the GC signs on the screen. The signed PDF is filed as backup on the change order and the hours and material flow into it. Cost to date is tracked against the not-to-exceed, with unsigned tickets shown separately so you can see what still needs a signature.
This guide describes common practice. Your subcontract, the prime contract and local law control, including who may sign tickets and notice periods. This is not legal advice.