How to request a time extension on an electrical change order

Electrical contractors price the money on a change and forget the days. Then the change order gets signed with zero added time, the extra work pushes the finish, and the delay ends up on your side of the ledger. Here is how to figure the days a change really adds, put them on the change order, and protect them when the GC won't agree.

Why the days belong on the change order

Under AIA A201 a change order is the written agreement on three things: the change in the work, the change in the contract sum and the change in the contract time. If the time line says zero, or is blank, most GCs and many courts will read the signed change order as your agreement that the change added no days.

Price the time with the money, every time. A change order you sign with no time adjustment is usually the end of the time argument for that change, even if the delay shows up later.

How many days does a change really add?

Not every change moves the finish date. What matters is whether the added work sits on the critical path, or uses up more float than the activity has.

Work out the duration

  • Labor days: labor hours divided by (crew size × hours per day). 240 hours with a crew of 3 at 8 hours is 10 working days.
  • Procurement: long-lead material counts too. Gear, generators, filters and lighting control panels with 10 to 14 week lead times often drive the date more than the install does.
  • Sequencing: work done alongside base scope may be absorbed; work that has to happen before or after something else (a shutdown, a ceiling close-in, an inspection) pushes it.
  • Float: subtract only the float that belongs to the affected activities, and say whose float it is if your contract addresses that.

Show it against the schedule

A number with no schedule behind it is easy to reject. Tie the request to the current contract or CPM schedule: name the activities the change touches, show where the new work goes (a short fragnet works well), and show the new completion date for your scope and, if it moves, the project.

What to put in the request

  1. The CO, CCD, bulletin or RFI number the change comes from.
  2. The days requested, working or calendar, matching how your contract counts time.
  3. The activities affected and why they are critical or why float is used up.
  4. Long-lead items with the supplier's quoted lead time.
  5. Any shutdowns, outage windows or access limits that set the sequence.
  6. What it costs to hold the date instead (acceleration), if the GC wants that option.

Giving the GC both numbers works well: Price A with the time extension, Price B with no added time and the overtime, extra crew or expediting it takes to hold the date. They choose, and you are covered either way.

When the GC says "no time"

  • Answer in writing that you are reserving your right to a time adjustment, and send it within the notice period in your subcontract. Under A201 (2017), claims, including claims for additional time, need written notice within 21 days unless your contract says otherwise.
  • Do not sign a change order that shows zero days if you believe it adds time. Strike the zero and write your days, or add an exception that time is reserved, and initial it.
  • Keep tracking: daily reports, manpower, and the dates the change work actually ran. The record is what proves the delay later.

Not sure the notice went out? Free notice letter tool. More on directed work in the CCD guide.

Common mistakes

  1. Pricing the money and leaving the time at zero.
  2. Counting install days but not the 12-week gear lead time.
  3. Asking for days with no schedule activities to back them up.
  4. Mixing working days and calendar days.
  5. Letting the 21-day (or shorter) notice window pass while waiting for the GC's answer.

Where software helps

Electrical Change Orders estimates the schedule impact of each change from its labor hours, crew size, long-lead material, sequencing and float. Upload the contract schedule (a PDF Gantt chart, a P6 .xer or an MS Project .xml) and it checks the change against the contractual completion date, and P6 and MS Project exports bring in float and logic. The proposal can show Price A with the time extension and Price B with no added time.

This guide describes common practice and the AIA A201 (2017) general conditions. Your subcontract, the prime contract and local law control, including notice periods and how time is counted. This is not legal advice.